Home / Blog / Solar Installation / DNO Approval: What is it and how does it work?
Solar Installation 9 min read

DNO Approval: What is it and how does it work?

By CRG Direct Team 1 September 2024

You must get DNO approval to export energy to the national grid. Find out what it is, how it works, and why there is such a long wait time.

What is DNO Approval?

DNO stands for Distribution Network Operator - the company responsible for the electricity network in your area. Before connecting any generation equipment (like solar panels) to the grid, you must notify or get approval from your DNO. This ensures the network can safely handle your exported electricity.

Why is it Required?

The electricity grid was designed for one-way flow - from power stations to homes. Solar panels reverse this flow, and DNOs need to:
  • Ensure network stability
  • Prevent overloading
  • Maintain power quality
  • Protect engineers working on lines
  • Plan future network capacity
  • G98 vs G99: Understanding the Difference

    G98 (Notification Process)

    For smaller systems:
  • System size: Up to 3.68kW per phase (11kW three-phase)
  • Process: Notification only - install then notify
  • Timeline: Notify within 28 days of commissioning
  • Response: Usually automatic acceptance
  • Cost: Free
  • G99 (Application Process)

    For larger systems:
  • System size: Above 3.68kW per phase
  • Process: Apply before installation
  • Timeline: 45-90 working days typically
  • Response: May require network studies
  • Cost: Free application, studies may cost
  • The DNO Application Process

    Step 1: Determine Your Requirements

  • Check system size (AC output)
  • Identify your DNO region
  • Decide G98 or G99 route
  • Gather system information
  • Step 2: G98 Notification Process

  • Install system with MCS installer
  • Complete commissioning tests
  • Submit G98 form online or post
  • Receive acknowledgment from DNO
  • Start exporting immediately
  • Step 3: G99 Application Process

  • Submit application before installation
  • DNO reviews network capacity
  • Possible network study if concerns
  • Receive offer with any conditions
  • Accept offer and pay any costs
  • Install system once approved
  • Final commissioning witnessed by DNO
  • UK Distribution Network Operators

    England and Wales DNOs

  • UK Power Networks: London, South East, East
  • Western Power Distribution: Midlands, South West, Wales
  • Northern Powergrid: Yorkshire, North East
  • Electricity North West: North West England
  • Scottish Power Energy Networks: Merseyside, North Wales
  • SSE Networks: Central Southern England
  • Finding Your DNO

  • Check your electricity bill
  • Use Energy Networks Association website
  • Ask your installer
  • Call 105 (power cut number)
  • Why the Long Wait Times?

    Current Challenges

    DNOs face unprecedented demand:
  • Solar installations up 50% year-on-year
  • Limited staff for assessments
  • Aging infrastructure needing upgrades
  • Complex calculations for each area
  • Regulatory requirements adding steps
  • Network Constraints

    Some areas experience:
  • Voltage rise issues
  • Thermal overloading
  • Reverse power flow problems
  • Protection system conflicts
  • Harmonic distortion
  • What Happens During Assessment?

    Network Studies Include

  • Voltage level analysis: Can network handle export?
  • Thermal capacity: Will cables overheat?
  • Fault level assessment: Protection systems impact
  • Power quality: Harmonic and flicker analysis
  • Geographic clustering: Other local generation
  • Possible Outcomes

  • Unconditional approval: Proceed with installation
  • Conditional approval: With export limits
  • Approval with costs: Network reinforcement needed
  • Temporary refusal: Until upgrades complete
  • Alternative connection: Different connection point
  • Export Limitation Devices

    When Required

    DNOs may mandate export limiting if:
  • Network constraints exist
  • Conditional approval granted
  • Cost-effective alternative to upgrades
  • Temporary measure planned
  • How They Work

  • G100 certified devices required
  • Dynamically limit export power
  • Allow full self-consumption
  • Typical limits: 3.68kW or zero export
  • Can be adjusted when network upgraded
  • Costs and Timescales

    Typical Timescales

  • G98 notification: Immediate installation
  • G99 simple: 6-8 weeks
  • G99 with study: 12-16 weeks
  • Complex cases: Up to 6 months
  • Appeals process: Additional 3 months
  • Potential Costs

  • Application: Free
  • Basic studies: Free
  • Detailed studies: £500-£2,000
  • Network reinforcement: £1,000-£50,000+
  • Alternative connection: Variable
  • Common Issues and Solutions

    Application Delays

    If experiencing delays:
  • Chase regularly: Weekly contact
  • Escalate: To DNO managers
  • Complain formally: If exceeding timescales
  • Contact Ofgem: For regulatory breach
  • Consider alternatives: Export limitation
  • Rejection Reasons

    Common issues:
  • Incomplete application forms
  • Wrong system details provided
  • Missing electrical diagrams
  • Incorrect DNO region
  • Previous applications not closed
  • Battery Storage Considerations

    Additional Complexity

    Batteries add requirements:
  • Must declare storage capacity
  • AC or DC coupled differences
  • Charge/discharge rates considered
  • Grid charging capabilities
  • Emergency backup features
  • G100 Compliance

    For export limitation:
  • Batteries must be included
  • Integrated control required
  • Failsafe operation essential
  • Regular testing needed
  • Future Developments

    Smart Grid Evolution

    Coming improvements:
  • Dynamic export agreements
  • Real-time network management
  • Flexible connections
  • Market-based solutions
  • Automated applications
  • Regulatory Changes

    Expected updates:
  • Streamlined processes
  • Shorter timescales
  • Digital applications only
  • Standardized national approach
  • Reduced bureaucracy
  • Tips for Smooth Approval

    Do's

  • ✅ Use experienced installers
  • ✅ Submit complete applications
  • ✅ Provide accurate information
  • ✅ Respond quickly to queries
  • ✅ Keep records of everything
  • Don'ts

  • ❌ Install before G99 approval
  • ❌ Modify system after application
  • ❌ Submit multiple applications
  • ❌ Provide incorrect details
  • ❌ Ignore DNO communications
  • Working with Your Installer

    Installer Responsibilities

    Good installers will:
  • Handle all DNO paperwork
  • Advise on requirements
  • Track application progress
  • Manage any issues
  • Ensure compliance
  • Your Responsibilities

  • Provide accurate information
  • Sign forms promptly
  • Pay any required fees
  • Inform of any changes
  • Keep documentation safe
  • The Witness Test Process

    For Larger Systems

    G99 installations may require:
  • DNO engineer attendance
  • Commissioning tests witnessed
  • Protection settings verified
  • Export limitation checked
  • Final approval granted
  • Preparation Required

  • System fully installed
  • All tests completed
  • Documentation ready
  • Safe access provided
  • Installer present
  • Alternative Solutions

    If DNO Approval Difficult

    Consider:
  • Smaller system: Stay under G98 limits
  • Export limitation: Accept constraints
  • Battery storage: Increase self-consumption
  • Phased installation: Start small
  • Different property: If multiple owned
  • Case Studies

    Successful G99 Application

    Manchester homeowner:
  • 6kW system proposed
  • Initial concerns raised
  • Export limitation accepted
  • Approved in 8 weeks
  • Full export allowed after 1 year
  • Complex Network Reinforcement

    Rural Scottish property:
  • 10kW system planned
  • Weak network identified
  • £15,000 upgrade quoted
  • Negotiated 50% contribution
  • System operational after 6 months

Conclusion

DNO approval is a crucial but sometimes frustrating part of the solar installation process. Understanding the requirements, timescales, and potential challenges helps set realistic expectations. While wait times can be long, especially for G99 applications, the process ensures safe and stable operation of the electricity network as renewable generation grows.

Working with experienced installers like CRG Direct significantly smooths the DNO approval process. We handle all applications, track progress, and manage any issues that arise. Our expertise with local DNOs and understanding of their requirements helps minimize delays and maximize your chances of straightforward approval.

Don't let DNO approval concerns delay your solar plans - contact us today for expert guidance through the entire process.

CRG Direct Team

Hampshire's leading solar installation and renewable energy specialists since 2017.

Share this article

Ready to Start Saving?

Contact our renewable energy specialists to discuss your solar installation or energy efficiency needs.