You must get DNO approval to export energy to the national grid. Find out what it is, how it works, and why there is such a long wait time.
What is DNO Approval?
DNO stands for Distribution Network Operator - the company responsible for the electricity network in your area. Before connecting any generation equipment (like solar panels) to the grid, you must notify or get approval from your DNO. This ensures the network can safely handle your exported electricity.
Why is it Required?
The electricity grid was designed for one-way flow - from power stations to homes. Solar panels reverse this flow, and DNOs need to:- Ensure network stability
- Prevent overloading
- Maintain power quality
- Protect engineers working on lines
- Plan future network capacity
- System size: Up to 3.68kW per phase (11kW three-phase)
- Process: Notification only - install then notify
- Timeline: Notify within 28 days of commissioning
- Response: Usually automatic acceptance
- Cost: Free
- System size: Above 3.68kW per phase
- Process: Apply before installation
- Timeline: 45-90 working days typically
- Response: May require network studies
- Cost: Free application, studies may cost
- Check system size (AC output)
- Identify your DNO region
- Decide G98 or G99 route
- Gather system information
- Install system with MCS installer
- Complete commissioning tests
- Submit G98 form online or post
- Receive acknowledgment from DNO
- Start exporting immediately
- Submit application before installation
- DNO reviews network capacity
- Possible network study if concerns
- Receive offer with any conditions
- Accept offer and pay any costs
- Install system once approved
- Final commissioning witnessed by DNO
- UK Power Networks: London, South East, East
- Western Power Distribution: Midlands, South West, Wales
- Northern Powergrid: Yorkshire, North East
- Electricity North West: North West England
- Scottish Power Energy Networks: Merseyside, North Wales
- SSE Networks: Central Southern England
- Check your electricity bill
- Use Energy Networks Association website
- Ask your installer
- Call 105 (power cut number)
- Solar installations up 50% year-on-year
- Limited staff for assessments
- Aging infrastructure needing upgrades
- Complex calculations for each area
- Regulatory requirements adding steps
- Voltage rise issues
- Thermal overloading
- Reverse power flow problems
- Protection system conflicts
- Harmonic distortion
- Voltage level analysis: Can network handle export?
- Thermal capacity: Will cables overheat?
- Fault level assessment: Protection systems impact
- Power quality: Harmonic and flicker analysis
- Geographic clustering: Other local generation
- Unconditional approval: Proceed with installation
- Conditional approval: With export limits
- Approval with costs: Network reinforcement needed
- Temporary refusal: Until upgrades complete
- Alternative connection: Different connection point
- Network constraints exist
- Conditional approval granted
- Cost-effective alternative to upgrades
- Temporary measure planned
- G100 certified devices required
- Dynamically limit export power
- Allow full self-consumption
- Typical limits: 3.68kW or zero export
- Can be adjusted when network upgraded
- G98 notification: Immediate installation
- G99 simple: 6-8 weeks
- G99 with study: 12-16 weeks
- Complex cases: Up to 6 months
- Appeals process: Additional 3 months
- Application: Free
- Basic studies: Free
- Detailed studies: £500-£2,000
- Network reinforcement: £1,000-£50,000+
- Alternative connection: Variable
- Chase regularly: Weekly contact
- Escalate: To DNO managers
- Complain formally: If exceeding timescales
- Contact Ofgem: For regulatory breach
- Consider alternatives: Export limitation
- Incomplete application forms
- Wrong system details provided
- Missing electrical diagrams
- Incorrect DNO region
- Previous applications not closed
- Must declare storage capacity
- AC or DC coupled differences
- Charge/discharge rates considered
- Grid charging capabilities
- Emergency backup features
- Batteries must be included
- Integrated control required
- Failsafe operation essential
- Regular testing needed
- Dynamic export agreements
- Real-time network management
- Flexible connections
- Market-based solutions
- Automated applications
- Streamlined processes
- Shorter timescales
- Digital applications only
- Standardized national approach
- Reduced bureaucracy
- ✅ Use experienced installers
- ✅ Submit complete applications
- ✅ Provide accurate information
- ✅ Respond quickly to queries
- ✅ Keep records of everything
- ❌ Install before G99 approval
- ❌ Modify system after application
- ❌ Submit multiple applications
- ❌ Provide incorrect details
- ❌ Ignore DNO communications
- Handle all DNO paperwork
- Advise on requirements
- Track application progress
- Manage any issues
- Ensure compliance
- Provide accurate information
- Sign forms promptly
- Pay any required fees
- Inform of any changes
- Keep documentation safe
- DNO engineer attendance
- Commissioning tests witnessed
- Protection settings verified
- Export limitation checked
- Final approval granted
- System fully installed
- All tests completed
- Documentation ready
- Safe access provided
- Installer present
- Smaller system: Stay under G98 limits
- Export limitation: Accept constraints
- Battery storage: Increase self-consumption
- Phased installation: Start small
- Different property: If multiple owned
- 6kW system proposed
- Initial concerns raised
- Export limitation accepted
- Approved in 8 weeks
- Full export allowed after 1 year
- 10kW system planned
- Weak network identified
- £15,000 upgrade quoted
- Negotiated 50% contribution
- System operational after 6 months
G98 vs G99: Understanding the Difference
G98 (Notification Process)
For smaller systems:G99 (Application Process)
For larger systems:The DNO Application Process
Step 1: Determine Your Requirements
Step 2: G98 Notification Process
Step 3: G99 Application Process
UK Distribution Network Operators
England and Wales DNOs
Finding Your DNO
Why the Long Wait Times?
Current Challenges
DNOs face unprecedented demand:Network Constraints
Some areas experience:What Happens During Assessment?
Network Studies Include
Possible Outcomes
Export Limitation Devices
When Required
DNOs may mandate export limiting if:How They Work
Costs and Timescales
Typical Timescales
Potential Costs
Common Issues and Solutions
Application Delays
If experiencing delays:Rejection Reasons
Common issues:Battery Storage Considerations
Additional Complexity
Batteries add requirements:G100 Compliance
For export limitation:Future Developments
Smart Grid Evolution
Coming improvements:Regulatory Changes
Expected updates:Tips for Smooth Approval
Do's
Don'ts
Working with Your Installer
Installer Responsibilities
Good installers will:Your Responsibilities
The Witness Test Process
For Larger Systems
G99 installations may require:Preparation Required
Alternative Solutions
If DNO Approval Difficult
Consider:Case Studies
Successful G99 Application
Manchester homeowner:Complex Network Reinforcement
Rural Scottish property:Conclusion
DNO approval is a crucial but sometimes frustrating part of the solar installation process. Understanding the requirements, timescales, and potential challenges helps set realistic expectations. While wait times can be long, especially for G99 applications, the process ensures safe and stable operation of the electricity network as renewable generation grows.
Working with experienced installers like CRG Direct significantly smooths the DNO approval process. We handle all applications, track progress, and manage any issues that arise. Our expertise with local DNOs and understanding of their requirements helps minimize delays and maximize your chances of straightforward approval.
Don't let DNO approval concerns delay your solar plans - contact us today for expert guidance through the entire process.